PROJECT FACTS
Project Consultant Engineering: LJA Engineering
City Project Manager: Mai-Theresa Bernal, P.E.
Contractor: Bay, LTD
Construction Inspector: James Ramirez
Liquidation Damages: $1,750
Award Date: July 2019
Construction Start: January 20, 2020
Anticipated Completion: July 31, 2021
Total Project Value: $11,462,907